| Clause No./ Heading |
Instead of |
Additions/Deletions/
or Read As |
| Add New para in clause 2.1.
|
|
In case of any inconsistency between the Supply Code 2005
and Tariff Order in force, the provisions and meanings contained in tariff
order in force at that time shall prevail over this Code. |
| Clause 2.2(u)
& 2.2(jj)
|
Replace words:
contracted load or maximum load whichever is higher
Occurring in the definitions of demand charge and load factor.
|
By words:
Maximum load
In these two definitions. |
| Clause 4.7(h)
|
In case the licensee is not in a position to provide a
meter, the applicant may procure the meter and MCB himself with the consent
of licensee, of approved make and specification fixed by the licensee
and the same shall also be deposited with the Licensee who after satisfying
himself about the accuracy of the meter and MCB on payment of test charges. |
(i) In case the licensee is not
in a position to provide a meter, the applicant may procure the meter
and MCB himself with the consent of licensee, of approved make and specification
fixed by the licensee.
(ii) The applicant shall deposit the meter & MCB, along
with test charges with the Licensee. After testing the accuracy of the
meter, the Licensee shall install the meter and MCB. |
| Clause 5.2 (f)
|
For all the 11 KV & 33 KV consumers, facility for remote
meter reading (GSM technique), and for distribution transformers,
remote meter reading (with facility of low power Radio) to extract data
from meter centrally, in order to have access on data as and when required.
|
For all the 11 KV & 33 KV consumers, the licensee shall
introduce the facility for taking remote meter reading (GSM technique),
and for distribution transformers, remote meter reading (with facility
of low power Radio) to extract data from meter centrally, in order to
have access on data as and when required.
|
| Clause 5.6(c)
|
a.In case meter is found O.K
.
(ii) In case the meter is found fast
..
(iii) If the consumer disputes
|
(i) . In case meter is found O.K
(ii) In case the meter is found fast
..
(iii) If the consumer disputes
. |
| Clause 6.10(iii)
|
In case a cheque is not encashed within 7 days of presentation
to the bank, the consumer shall forfeit rebate and the Licensee may levy
surcharge and also withdraw the facility of payment by cheque.
|
In case a cheque is not encashed within 7 days of presentation
to the bank, the consumers rebate shall be forfeited, and the Licensee
may levy surcharge, and also withdraw the facility of payment by cheque.
|
| Annexure 6.3(c)
Reason:
To correct typo error |
Assessment in case of Unauthorized use of Electricity
(For cases covered under (i), (ii), (iii), and (v) of the definition
of unauthorized use) |
Deleted:
(For cases covered under (i), (ii), (iii), and (v) of the definition
of unauthorized use) |
| Annexure 6.3(c) continued. |
Replace Heading:
For cases covered under (iv) of the definition of unauthorized use |
Replace with:
For cases where usage of electricity is for other purpose than authorized |
| 7.7.2.
|
New Connections/Disconnections/Reconnections and Related
matters:
(a) If a distribution licensee fails to provide new connection to an
applicant within the period specified in clause 4
..Forum
|
(a) If a distribution licensee fails to provide new connection
to an applicant within the period specified below.
Forum
For LT connections, where pole exists - within 7 days, If new poles are
required: within 30 days.
For HT cases where works required:
(a) 45 days for loads at 400 Volts,
(b) 60 days at 11 KV,
(c) 120 days at 33 KV,
(d) 300 days for loads to be connected at 132 KV
For un-electrified areas:
(a) Where augmentation from newly existing work is possible
180 days;
(b) Where new work or grid needs to be laid - 1year;
(c) In case of Isolated Consumer - 180 days
Disconnection/Reconnection:
Reconnection after removal of cause of disconnection 24 hours
|
| 7.7.3 |
Metering as given in chapter 5 of the Code |
Metering as given below:
- Replacement of defective meter after test report: 15 days
- Replacement of Burnt meter: 3 days
|
| 7.7.4 |
Billing - as given in chapter 6 of the Code |
Billing - as given below:
Reduction/Enhancement of load 30 days Termination of agreement
-30 days
Carry forward of fictitious arrear -one cycle
|
|
7.7.5 |
Transfer of Ownership and Conversion of Services as given
in chapter 4 of the Code |
Transfer of Ownership and Conversion of Services as given
below:
Transfer of Ownership: 30 days
|
| Clause 7.9 (b)(i)proviso
|
Provided that compensation shall be applicable to only those
consumers who have no arrears on electricity dues, and conditions, not covered
or incidental to factors mentioned in clause 9.1 of this code.
|
Provided that compensation shall be applicable to only those
consumers who have no arrears on electricity dues, and on conditions, which
are not covered or incidental to factors mentioned in clause 9.1 of this
code.
|