| Sr. No. |
Load |
Authority for permission |
| 1 |
Up-to 7.5 KW |
SDO Domestic & Commercial LMV4 |
| 2 |
25 KW |
AGM |
| 3 |
75 KW |
GM |
| 4 |
Above 75 KW |
MD |
- If Transformer installation is required then for every connection permission
is required from MD Office.
- For Industrial Connection applicant will submit the application to GM
Industries. On every Friday all the applications will be handed over
to KESCo representative. He will hand over all the applications to Industrial
Connection Committee.
- Industrial Connection Committee takes the decisions regarding the new connection
for the industries. If the load is up-to 250 KVA then Account officer,
PA (Technical) and Executive Engineer (Transmission) can release
it. For load more than 250 KVA Permission is required from MD, DGM
(Transmission) /GM and Deputy CAO.
Documents Required for NEW Connection
- Application Form
- Address Verification Proof
- Photographs
- B & L Form (For Certification of Wiring Load)
- Agreement ( On a Stamp paper of Rs. 100/- For Commercial
Connection and On Plain Paper for Domestic Connection)
- Processing Fee of Rs. 50/- for both type of Connections
** After load Sanction KESCo provides an estimate to Consumer. When Consumer
submits the fee, KESCO releases the connection.
|