Sr. No.

Load

Authority for permission
1
Up-to 7.5 KW
SDO Domestic & Commercial LMV4
2
25 KW
AGM
3 75 KW GM
4 Above 75 KW MD
  • If Transformer installation is required then for every connection permission is required from MD Office.
  • For Industrial Connection applicant will submit the application to GM Industries. On every Friday all the applications will be handed over to KESCo representative. He will hand over all the applications to Industrial Connection Committee.
  • Industrial Connection Committee takes the decisions regarding the new connection for the industries. If the load is up-to 250 KVA then Account officer, PA (Technical) and Executive Engineer (Transmission) can release it. For load more than 250 KVA Permission is required from MD, DGM (Transmission) /GM and Deputy CAO.

Documents Required for NEW Connection

  1. Application Form
  2. Address Verification Proof
  3. Photographs
  4. B & L Form (For Certification of Wiring Load)
  5. Agreement ( On a Stamp paper of Rs. 100/- For Commercial Connection and On Plain Paper for Domestic Connection)
  6. Processing Fee of Rs. 50/- for both type of Connections

 

 


** After load Sanction KESCo provides an estimate to Consumer. When Consumer submits the fee, KESCO releases the connection.